You have witnessed the transformation of the solar industry over more than a decade. Looking back today, what developments have changed the industry the most?
I’ve been in the PV industry since 2009. Since then, I’ve seen some highs and lows. When we started ESG in 2016, German solar expansion was at an absolute low point. Only 1.5 gigawatts of photovoltaics were installed annually. For comparison: that’s an amount we currently sometimes deploy in a single good month. That shaped us as a company because we initially grew faster than the market. Alongside rooftop systems, we consciously entered the utility-scale solar sector—a smart decision, as it turned out. We then played a major role in shaping the second solar boom driven by COVID-19 and the Ukraine war. That boom leveled off as electricity prices normalized, and was replaced by something else...
We are currently seeing a massive expansion in battery storage. In your view, is this the next major developmental step in the energy transition, and how has this changed your company?
My thesis is: we are now facing the first storage boom! We are no longer talking in isolation about individual solar modules, their yield, or warranties. We are now talking about storage, intelligence, and when and how charging happens. The system is clearly in the foreground, rather than the individual component. That’s why we have continuously expanded our portfolio. In addition to the residential, commercial, industrial, and utility-scale solar segments, we added utility-scale BESS two years ago. This year, charging infrastructure for heavy-duty traffic followed. Going forward, storage and charging infrastructure projects will take on huge importance for us as a company. Solar is always part of it. It remains part of the whole, but in the list of what belongs to a charging infrastructure project, it is mentioned last.
For the BESS project at Sandershäuser Berg, you implemented a utility-scale storage system. What challenges do you particularly remember during the planning and implementation phases?
We have already implemented two utility-scale BESS projects and currently have more under construction. There was a learning curve with those first two projects that cost us both time and money. In the end, our customers benefit from these experiences. We make it a rule never to test new technologies on the customer. We managed the procurement of the first two storage systems in-house. We researched, analyzed, and weighed up who the right partner was. That was at a point when we thought we had answered 80 out of 100 questions, only to discover there were 160 questions that needed answering. The challenge was twofold: finding a manufacturer with a good product, and finding a partner who was accessible, reliable, and continuously provided information. It’s not just about a good product; ultimately, it’s also about the people you work with.
What do you remember most positively from your first two storage projects?
We were able to demonstrate the typical strengths of a mid-sized enterprise in a particularly impressive way: speed, courage, pragmatism, and solution-oriented action. We were able to answer those missing 80 questions before the enclosures were on site. That takes effort, but it makes the team proud in the end. A municipal utility or a major corporation can't operate like that. They resolve 159.5 questions first, wait for supervisory board resolutions, and build two years later. We set the pace. Even bureaucratic hurdles didn't stop us. We applied for the grid connection early with the municipal utilities, before the big wave of applications started. With the building authorities, direct communication is what counts. We drive there and explain the projects in person. For fire protection and noise control, we work with specialized consultants.
You faced the decision of procuring storage systems yourself. How did you approach this endeavor? What were your takeaways from the process?
For the sake of speed, we initially chose known, reliable partners. These were mostly large European suppliers where we relied on local contacts and solid warranty claims. The selection of storage suppliers is highly complex, and warranty conditions are sometimes opaque. That is why we now rely on external support.
What would you advise entrepreneurs who, like you, face the decision of selecting the right one from a multitude of available suppliers?
It makes absolute sense to have a partner like you, who knows their way around the highly complex storage supplier market, as a copilot. We see for ourselves that a thorough qualification of different suppliers and cells takes time. Therefore, there is always the additional question of the project's timeline. Of course, I could also say, look at the references of operational systems. However, the reality is that we have innovation cycles. This means that for newer storage systems, there isn't always sufficient real-world data because these systems haven't been in operation long enough. In five years, I already expect the first repowering wave, meaning parts of the storage systems will need to be replaced because they are degraded. This is due to the current market trend of installing cheap and inferior technology, but in the end, it will damage the reputation of the entire industry and cause higher costs than were foreseeable at the time of procurement.
If you could wish for something that would make your work with BESS easier and/or more profitable in the future, what would it be?
Binding rules instead of arbitrary actions by individual players. With flexible grid connection agreements, every grid operator currently defines their own specifications. We need nationwide standards and clear language to get people on board. Maybe I’ll become a politician later in life.
If the framework conditions are right, then we can deliver. The solar industry has already proven this, and the wind and biogas industries are proving it too. A model with, say, 1,200 hours of curtailment is easy to calculate. If that helps the grid and allows us to connect twice as many storage systems as a result, I’m fully on board. That way, we increase grid utilization without endlessly laying new cables. What slows us down is the fragmentation across 850 Distribution System Operators (DSOs), who are often heavily stretched in terms of personnel.
What is the best part of your job for you?
The great thing is that we are working on renewable energy systems and really making things happen! The huge motivation is seeing the impact of your work. For example, if we decide to build a utility-scale BESS, we accompany the project from the initial idea right through to implementation. When the enclosure is standing there a year later and we celebrate the opening, it’s an incredible feeling.
So you’re setting a few good examples and motivating others as well?
We have actually earned a reputation as innovators in the region. We built the first utility-scale BESS in the Kassel area and the first megawatt charger for electric trucks in Hessen. We take a disruptive approach. A small example: we offer the truck charger at a charging rate of 29.9 cents. But the standard is more like 39 or 40 cents. That is disruptive.
NOVUM News

Large-format battery cells in BESS: Gaining ground in the market and put to the test at NOVUM
Up to 6.9 MWh in a single standard container: Large-format LFP cells exceeding 500 Ah are challenging the incumbent 314 Ah standard cells for market dominance. The value proposition sounds promising: they can reduce component counts, increase energy density at the system level, and lower initial integration costs. [1] However, this leap in scale raises several physical questions, as increasing dimensions escalate requirements for cooling, fire safety, and degradation control. Because we at NOVUM are already analyzing these new large-format cells in our quality assessments, we checked in with our battery experts: How much do we know about their design, behavior, and safety, what critical factors must be considered, and what does this mean for BESS procurement?

Commissioning is only the beginning
Utility-scale battery energy storage systems (BESS) are expected to deliver reliable performance over many years. Two European examples highlighted in pv magazine ESS News demonstrate just how closely long-term revenues are tied to technical obligations. For investors and operators, factoring long-term performance trends into account right from the planning stage is therefore essential.

Driving new energy systems with speed, courage, and pragmatism
With his company Energiesysteme Groß (ESG), Björn Groß built the first utility-scale battery energy storage system (BESS) in the Kassel region. In our interview, he revealed that he generally takes a "disruptive" approach. The solar industry is his home, and the whole world of renewable energy systems is his new domain. Bjön talks about his initial experiences with utility-scale BESS procurement, his motivations, and his future goals.